On 10/19/2014, Tepco announced that they have already completed transferring 1,320 of 1331 spent fuel assemblies from Reactor 4 pool.
The rest of 11 spent fuel assemblies to include 3 damaged assemblies are to be transferred with the next lot planned by the end of November.
Still 180 of 202 new fuel assemblies are remaining in the pool, but Tepco announces the radiation level is low enough for human worker to manually handle.
So far, they have transferred the casks for 61 times.
http://www.tepco.co.jp/decommision/planaction/removal-j.html